|
|
| w e e k l y
p r o g r e s s r e p o r t s
Re-discover Your Library
 August Flood
Photographs
|
Week
of
June 16, 2008
The Demolition of the Community Room at
Arlington was completed on Thursday, June 19th.
|

Week
of
June 9, 2008
This week work was started on
the interior cement block walls. Miller Contracting did prep work on Monday,
began laying blocks on Tuesday, and by The end of the day Wednesday they had
5 rows of blocks up on a major section of the project. County Electric also
worked these days fitting the new walls with electrical outlets. The base
/vault for the new electric transformer was Also excavated and installed
this week (Thursday) between the parking garage Ramps.
Work at the Arlington branch
involved meeting American Electric Power to have the electric meter and
service line disconnected. Charles Associates Will begging demolition on the
rear section of the building early next week.
We have contacted Larry Fast,
a structural engineer to evaluate the remaining Portion of the building
after the demolition work is completed.
|
Week
of
June 2, 2008
This week, Jack's plumbing spent a lot of
time and made significant progress on the
new sanitary drain lines in the basement. Concrete had to be cut, then
shallow excavations
followed by new PVC drain lines and back fill. The new diversion tank for
our flood response
plan also arrived. Concrete block that will be used to build the new
interior walls in the lower
level also arrived this week. Sub contractors from Miller Contracting were
in part of one day
and marked the location of these walls on the existing floor. Cory and I
made one trip to the
recycling center with the old dumpster enclosure metal, and received over
$500 for the load.--Dick Taylor
|
Week
of
May 27, 2008
Progress was made this week on the interior
work. Jack's HVAC cut the concrete slab in the
basement where the new sanitary line check valves will go, and the
areas where new plumbing will
be added for the new room configuration. Miller Contracting did more
work on demolition of the old
ceiling tiles, door frames, and lightning fixtures. Cory and I made
another trip to the recycling center
with scrap metals and have now recovered nearly $600 from these
scraps for the Library.--Dick Taylor
|
Week
of
May 22, 2008
After a long wait, major reconstruction activity began here at FHCPL
this week. On Tuesday, there were workers here starting demolition work in the
basement, removing old door frames and hardware, plumbing, and ceiling
tile grids. Wednesday, additional work was done on exterior tasks with concrete cutting, dumpster enclosure removal,
and tree cutting near the parking garage ramps. The parking garage was officially closed, and will
remain closed for the duration of the reconstruction period. We learned that
utility transfers to new equipment will require short interruptions in our power feed, and may require
us to close the building at some point in the process for at least 2
days. --Dick Taylor
|
Week
of
May 12, 2008
More work was done this week on the new natural gas line and meter
setting by Marlin White Contractors. They also worked inside removing many
internal gas lines and chilled water pumps. We have initiated a scrap metal recycling
agreement with the general contractor which will allow FHCPL to receive proceeds from all the old pipes
and structural steel as the project moves forward. Ryan Guth of Miller Contracting has assured us
that a construction schedule will be issued yet this week. We have decided to relocate our dumpster to
the FHCPL parking lot on the NW corner of Cory and Front Streets to
allow continued access thru the summer.--Dick Taylor |
Week
of
May 12, 2008
|
Week
of
April 28, 2008
This week we learned a little more
about the time line for our major
reconstruction work here at FHCPL. Ryan Guth of Miller Contracting
said
the interior demolition will begin around May 8th, and the exterior
sanitary
holding tank work should begin by the 15th. Structural steel has been
ordered, and the main natural gas line has been excavated near the
parking
garage entrance.
There will be a new electric transformer located in that same
area,
and the mid-sized trees growing there will need to be removed. Miller
Cont.will be the planning manager, and Ryan should have a project schedule for us in the next few days. He has informed me that the old Community Room will
not see demolition work until late June, so the staff will be
able
to continue using that space for their breaks and lunch for now. --Dick
Taylor
|
Week
of
April 21, 2008
Friday, April 18th Dave Hand
from subcontractor (Custom Home) was in and explained the
function and design of the new lift for the Technical Services addition.
We decided to reverse
the door opening so that it will open back against the brick wall rather
than opening out, and
creating a bit of a barrier for users. Cory was able to get all of our
excess furnishings moved
to the north end of our parking garage, so that area will be available
for contractors to use
and store equipment. We got word from our general contractor that the
parking garage will
probably be closed in the first couple of weeks of May, and stay closed
thru the duration of
the construction process.--Dick Taylor
|
Week
of
April 14, 2008
Preliminary work and
organizational meetings have been conducted this week as we prepare for
the onset of major flood recovery construction in the next two weeks.
Our main natural gas feed line has been re-routed by workers from Marlin
White, and other workers have begun dismantling some of the HVAC
components in the basement. We have decided to close the underground
parking garage to all traffic through the major construction phase of
this project for safety reasons. Patron and staff parking will be
available in our parking lot located on the NW corner of Front St. and
Cory St. as well as on Broadway for limited time slots (see signs).
Thanks for your continued patience as we strive to provide a flood proof
building over the next several months.--Dick Taylor |
Week
of
April 7, 2008
Work begins on the construction phase of the flood
recovery project. Marlin White and Sons Construction began work on the
new 4" gas line that will feed the new boilers in the new Mechanical
Building on the west side of our building. They had to bore through the
Parking Garage Wall, and route the new line over the entrance gate to
the Parking Garage. Work also began on the individual HVAC control boxes
in the basement level. --Dick Taylor
We are happy to report that Construction is now
underway. If we need to make changes in the Parking at the Main Library,
we will post it here. --Carol Dunn
|
Week
of March 17, 2008
FEMA approved $1,900,311.69 for construction and
mitigation efforts. The 75% that FEMA will pay is $1,425,233.77. The
State of Ohio will pay 12.5% and FHCPL will have to pay 12.5%. The Board
of Trustee's will be meeting on March 18th to approve construction and
to accept the FEMA approved and obligated dollars to be used towards the
flood recovery project. The construction and mitigation efforts include
the reconstruction of the lower level, remodeling of the Community Room
to house Administration and Technical Services. The project also
includes moving the mechanical systems above the base flood elevation
level. We appreciate your understanding and patience during all of the
changes.--Kelly Foust
|
Week
of February 25, 2008
The Findlay-Hancock County Public Library (FHCPL) has
been working with the Federal Emergency Management Association (FEMA)
since President Bush declared the City of Findlay a disaster area on
September 11, 2007. Many FEMA representatives toured the building to
assess the damage and to assist with the necessary steps to help FHCPL
seek funding.
The Ohio Emergency Management Association (OEMA) is currently in the
process of reviewing the Project Worksheets from FEMA. OEMA will be
turning in the Project Worksheets to Washington for final approval. It
is hopeful that Washington will review and approve them fairly quickly.
Construction cannot begin until the funds have been approved and
obligated to the State of Ohio. After funding is approved, FHCPL will
work with the State of Ohio to receive funds as a reimburseable expense
at 75%. The State of Ohio will reimburse at 12.5%, leaving FHCPL to pay
the remainder.
Project Worksheets are forms to document the scope of the work and the
cost estimate for the project. The Project Worksheets supplies FEMA with
the information necessary to approve the work along with costs estimates
prior to funding the project. FHCPL's Project Worksheet is considered a
large project due to the proposed construction and mitigation.
The construction project involves reconstruction of the lower level,
adding a floor in the Children's Department above the atrium, adding a
floor in the Community Room to accommodate office space for
Administration and Technical Services. The project also includes adding
a mechanical room elevated at a higher level to lessen exposure (damage
and financial) to future floods. -- Kelly Foust
|
Week
of February 6, 2008
The Main
Library closed due to Street Flooding. We received 2 inches of water in
the garage, and we have taken on a bit of water in the basement. We are
locating the Administration and Technical Services offices upstairs till
we go into construction. |
Week
of February 4, 2008
Future
plans for the lower level include: a designated Volunteer space, a new
Community Room and Book Cellar. Charles Construction is the project
manager. Morrison Kattman Menze is the architect for the project. |
Week
of
December 3, 2007
The Main Library has reopened. We are working with FEMA to
mitigate the basement area and our Community Room.
|
Week
of November 5-9, 2007
The Children's and AV departments are being carpeted this week. The
library has decided to combine these 2 desks into one and call it the
"Information Desk". It will be located in front of the Southwest Window.
|
Week
of October 29-Nov.3., 2007
The staff finish painting the AV Offices
and the Computer Lab. A new floor is being put down in the lobby.
Many caring people have
contacted us to offer donations of books. While we much appreciate any
offers of assistance, the best way to help your library at this early
stage of our rebuilding process is to donate funds.
We will gratefully accept donations to assist
with recovery. You may contribute to the Findlay-Hancock County
Public Library Relief Fund at any Fifth Third Bank or send a
check to: Fifth Third Bank, 337 South Main Street, Findlay, Ohio
45840. The Findlay-Hancock County Public Library is funded
through the Ohio Library Legislative Fund and does not
receive funding via the United Way, the American Red Cross or
any other local relief efforts.
|
Week
of October 22-26, 2007
Children's Storytime is now being held at
the Stately Raven Bookstore on Tuesdays and Thursdays at 10:30 a.m. This
is open to Children of all ages. 1315 North Main Street,
419-427-2814
Volunteers help move all the Childrens Books and AV materials. New
carpeting comes to these 2 departments on November 5th.
Library Book Truck
Brigade makes an appearance at the Halloween Parade on October 23.
|
Week
of October 15-19, 2007
New phone system is installed and staff takes training on Voice Mail and the
new features.
OPLIN calls the AT&T Engineers and they say we may have Internet
service restored as early as mid-November.
Childrens and AV offices are painted a
bright and cheery color. |
Week
of October 7-13, 2007
New phone system arrives on Wednesday.
Tuesday October 9th: almost 200 patrons show
up to check out books at the Arlington Branch Library.
Library closed on Columbus Day, October 8th. The Book Drop at the Main
Library is closed. |
Week
of September
30-October
6, 2007
On October 2 Library Board contracts with Charles Construction to restore
Lower Level and make improvements.
Inmates from the Hancock County Jail help with stripping old slate and
landscaping.
Administration continues to prepare documentation for FEMA.
|
Week
of September
23-29,
2007
Library begins to utilize volunteers from the community to help with Flood
Recovery.
|
Week
of September
16-22,
2007
Re-assigned staff members help with clean up, shelve materials and
landscaping. |
Week
of September
9-15, 2007
Bookmobile and Arlington Branch re-open on September 10.
|
Week
of September 2-8, 2007
The Board of Trustee's held a public meeting at the Lodge at Riverbend Park
on September 5th at 7:30 p.m. The meeting focused on Library Recovery
efforts with a nice showing of concerned citizens, Hancock County Genealogy
Society Members, retired staff members and Friends of the Library.
The first week of September Library Employees break up into teams and work
quickly to establish services at Arlington Branch Library with a temporary
Internet Cafe. The SEO Delivery Service is relocated to the Community Room
at the Arlington Library, and the Bookmobile gets ready to open in locations
around the county and in the library parking lot seven days a week. |
Week of
August 26-September 1, 2007
On August 30 two OPLIN engineers come to the Arlington Branch and re-route
the internet so the Branch Library can reopen with internet running straight
to Columbus on the T1 line.
The library employees man a
booth at the Hancock County Fair August 29-September 3.
WebServer is relocated
offsite and
www.findlaylibrary.org
reestablishes service on the WWW.
Main Library has been
stripped of all contents in the lower level including drywall and ceiling
tiles. Dehumidifiers are running in the upper level to control mold and save
our 6 million dollars worth of library materials. |
Week of August 21, 2007
As the flood receded, the library hired Tri-Weh, a recovery team
out of Cincinnati to reclaim the Library. Over a million gallons
of water was pumped from the building in a 2 day period. All services
were destroyed or damaged in the flood: furnace, electric, internet,
phones, security, paging, fire alarm, sprinkler system etc. This also
included the internet at our Arlington Branch, which comes directly
through the Main Library in Findlay. Early Tuesday Morning, on
August 21, as much as 9 inches of rain fell over parts of Hancock
County. To our East, parts of Wyandot County received 15 inches of rain
in a few hours. The Blanchard River began to rise and flooding took
place over much of the area. Twelve library employees showed up
for work, and spend most of the day bringing up essential materials from
the Lower Level, which included the Clerk Treasurer's Office materials.
The rest of the employees were stuck in their homes with no way out.
That evening the entire lower level went under water, and downtown
Findlay experienced the worse flood in the city's history.
Monday, August 20 the library closed as usual at 8:30 p.m. A light rain
was falling, with no indication of the incredible rainfall that was to
happen just hours later. Back
|
Summary, Dick Taylor, Facilities Manager of the
Findlay-Hancock County Public Library ,
MAY 2008
Findlay
Hancock Co. Public Library is located in Findlay, the Hancock Co. seat.
Our area was originally part of the great black swamp, thus very flat,
and drains slowly. Our building had a 15,000 sq ft furnished basement,
an 11,000 sq ft underground parking garage, and a community room and
lobby consisting of about 2000 sq ft at ground level. The collection and
main operations are on our 25,000 sq ft upper level which lies about 5'
above ground level.
On
August 21st remnants of hurricane Erin passed over the Findlay area
and stalled out, dumping almost 10" of rain through out the entire
water shed of the Blanchard river. The river runs thru the city of
Findlay, and only several hundred feet from our building. Our flat
topography results in a slow rise of river levels, our history of
flood issues had educated us to know that this unusual amount of
rain would cause massive flooding, so we closed the building the day
after the storm and began moving important items upstairs. What we
learned was that human nature had allowed us to "store" much more
inventory in our available spaces than we had time and energy to
move upstairs without a clear plan.
Only a
small portion of the staff was able to make it to the building as
roads began to close due to the rising water levels. We were able to
move most of the electronics, files, books in storage, valuable
supplies, and personal items up to the main floor. But without a
solid flood evacuation plan, we were unable to save many supplies,
NO furnishings nor any of our mechanical & electrical systems. We
received 90" of flood water in the basement, and several inches on
the ground floor community room. Along with the muddy flood water,
came sewage back up, a few small fish, and worst of all, our
elevator control room was also located in the basement, and the
hydraulic oil reservoir emptied 60 gallons of oil to the surface
coating everything with a slimy oily mud.
Our
dollar loss for clean up, mitigation, inventory replacement, and
reconstruction stands at over $2 million, but the untold loss of
community service is much harder to assess. We were "lucky" compared
to many other county and city agencies, as our history of flooding
pushed us to secure flood insurance after a more minor 1997 event.
Our insurance paid for our entire cleanup and dry out, as well as a
portion of our inventory replacement. And as a result of our
proactive flood response and insurance coverage, FEMA has come
forward with a very responsible mitigation grant.
Our
Main Library was closed to the public for over 12 weeks. During that
time we extended hours at our one branch facility ( 10 miles south
of Findlay ), and added stops and hours to our bookmobile service
through out the city and county. We opened back up for major
services on December 3, 2008, and began the slow process of
evaluating future needs and exposures. FEMA grant spending requires
an effort to move affected services up and out of the reach of
future flooding. We have worked with an architect to add second
floors in two areas, as well as constructing a new elevated
mechanical room on the outside of our building to accomplish this .
After a
summer of construction, we will have all of our staff services and
mechanical/electrical components up above our 100yr flood level. We
will also install a sanitary waste holding tank so that during
future flood events we will be able to keep our restrooms open for
staff and public use. Basement use in the future will be limited to
public meeting rooms, staff craft areas, our friends book sales
area, and maintenance operations. We will require all inventory
storage and furnishings to be wheel mounted, and sized so that they
fit into our elevator .
Back
| |
|