HOME>>               Main Library Catalog>>            Arlington Branch Catalog>>            Bookmobile Catalog>>     

 
w e e k l y    p r o g r e s s    r e p o r t s                             Re-discover Your Library


August Flood Photographs



 

Week of June 16, 2008

The Demolition of the Community Room at Arlington was completed on Thursday, June 19th.

 


 Week of June 9, 2008

This week work was started on the interior cement block walls. Miller Contracting did prep work on Monday, began laying blocks on Tuesday, and by The end of the day Wednesday they had 5 rows of blocks up on a major section of the project. County Electric also worked these days fitting the new walls with electrical outlets. The base /vault for the new electric transformer was Also excavated and installed this week (Thursday) between the parking garage Ramps.

Work at the Arlington branch involved meeting American Electric Power to have the electric meter and service line disconnected. Charles Associates Will begging demolition on the rear section of the building early next week.

We have contacted Larry Fast, a structural engineer to evaluate the remaining Portion of the building after the demolition work is completed.

 

 


 Week of June 2, 2008

This week, Jack's plumbing spent  a lot of time and made significant progress on the
new sanitary drain lines in the basement. Concrete had to be cut, then shallow excavations
followed by new PVC drain lines and back fill. The new diversion tank for our flood response
plan also arrived. Concrete block that will be used to build the new interior walls in the lower
level also arrived this week. Sub contractors from Miller Contracting were in part of one day
and  marked the location of these walls on the existing floor. Cory and I made one trip to the
recycling center with the old dumpster enclosure metal, and received over $500 for the load.--Dick Taylor


 Week of May 27, 2008

 

Progress was made  this week on the interior work. Jack's  HVAC cut the concrete slab in the
basement  where the new sanitary line check valves will go, and the areas where new plumbing will
be added for the new room configuration. Miller Contracting did more work on demolition of the old
ceiling  tiles, door frames, and lightning fixtures. Cory and I made  another trip to the recycling center
with scrap metals and  have now recovered nearly $600  from  these scraps  for the Library.--Dick Taylor


 Week of May 22, 2008

After a long wait, major reconstruction activity began here at FHCPL this week. On Tuesday, there were workers here starting demolition work in the basement, removing old door frames and hardware, plumbing, and ceiling tile grids. Wednesday, additional work was done on exterior tasks with concrete cutting, dumpster enclosure removal, and tree cutting near the parking garage ramps. The parking garage was officially closed, and will remain closed for the duration of the reconstruction period. We learned that utility transfers to new equipment will require short interruptions in our power feed, and may require us to close the building at some point in the process for at least 2 days. --Dick Taylor

 


 Week of May 12, 2008

More work was done this week on the new natural gas line and meter setting by Marlin White Contractors. They also worked inside removing many internal gas lines and chilled water pumps. We have initiated a scrap metal recycling agreement with the general contractor which will allow FHCPL to receive proceeds from all the old pipes and structural steel as the project moves forward. Ryan Guth of Miller Contracting has assured us that a construction schedule will be issued yet this week. We have decided to relocate our dumpster to the FHCPL parking lot on the NW corner of Cory and Front Streets to allow continued access thru the summer.--Dick Taylor


 Week of May 12, 2008

 


 Week of April 28, 2008

This week we learned a little more about the time line for our major reconstruction work here at FHCPL.  Ryan Guth of Miller Contracting said the interior demolition will begin around May 8th, and the exterior sanitary holding tank work should begin  by the 15th. Structural steel has been ordered, and  the main natural gas line has been excavated near the parking garage entrance.
There will be a new electric transformer located in that same area, and the mid-sized trees growing there will need to be removed. Miller Cont.will be the planning manager, and Ryan should have a project schedule for us in the next few days. He has informed me that the old Community Room will not see demolition work until late June, so the staff will be able to continue using that space for their breaks and lunch for now. --Dick Taylor


 Week of April 21, 2008

Friday, April 18th Dave Hand from subcontractor (Custom Home) was in and explained the
function and design of the new lift for the Technical Services addition. We decided to reverse
the door opening so that it will open back against the brick wall rather than opening out, and
creating a bit of a barrier for users. Cory was able to get all of our excess furnishings moved
to the north end of our parking garage, so that area will be available for contractors to use
and store equipment. We got word from our general contractor that the parking garage will
probably be closed in the first couple of weeks of May, and stay closed thru the duration of
the construction process.--Dick Taylor

 


 Week of April 14, 2008
 

Preliminary work and organizational meetings have been conducted this week as we prepare for the onset of major flood recovery construction in the next two weeks. Our main natural gas feed line has been re-routed by workers from Marlin White, and other workers have begun dismantling some of the HVAC components in the basement. We have decided to close the underground parking garage to all traffic through the major construction phase of this project for safety reasons. Patron and staff parking will be available in our parking lot located on the NW corner of Front St. and Cory St. as well as on Broadway for limited time slots (see signs). Thanks for your continued patience as we strive to provide a flood proof building over the next several months.--Dick Taylor


 Week of April 7, 2008

Work begins on the construction phase of the flood recovery project. Marlin White and Sons Construction began work on the new 4" gas line that will feed the new boilers in the new Mechanical Building on the west side of our building. They had to bore through the Parking Garage Wall, and route the new line over the entrance gate to the Parking Garage. Work also began on the individual HVAC control boxes in the basement level. --Dick Taylor
 

We are happy to report that Construction is now underway. If we need to make changes in the Parking at the Main Library, we will post it here. --Carol Dunn
 


 Week of March 17, 2008

FEMA approved $1,900,311.69 for construction and mitigation efforts. The 75% that FEMA will pay is $1,425,233.77. The State of Ohio will pay 12.5% and FHCPL will have to pay 12.5%. The Board of Trustee's will be meeting on March 18th to approve construction and to accept the FEMA approved and obligated dollars to be used towards the flood recovery project. The construction and mitigation efforts include the reconstruction of the lower level, remodeling of the Community Room to house Administration and Technical Services. The project also includes moving the mechanical systems above the base flood elevation level. We appreciate your understanding and patience during all of the changes.--Kelly Foust


 


 Week of February 25, 2008

The Findlay-Hancock County Public Library (FHCPL) has been working with the Federal Emergency Management Association (FEMA) since President Bush declared the City of Findlay a disaster area on September 11, 2007. Many FEMA representatives toured the building to assess the damage and to assist with the necessary steps to help FHCPL seek funding.

The Ohio Emergency Management Association (OEMA) is currently in the process of reviewing the Project Worksheets from FEMA. OEMA will be turning in the Project Worksheets to Washington for final approval. It is hopeful that Washington will review and approve them fairly quickly. Construction cannot begin until the funds have been approved and obligated to the State of Ohio. After funding is approved, FHCPL will work with the State of Ohio to receive funds as a reimburseable expense at 75%. The State of Ohio will reimburse at 12.5%, leaving FHCPL to pay the remainder.

Project Worksheets are forms to document the scope of the work and the cost estimate for the project. The Project Worksheets supplies FEMA with the information necessary to approve the work along with costs estimates prior to funding the project. FHCPL's Project Worksheet is considered a large project due to the proposed construction and mitigation.

The construction project involves reconstruction of the lower level, adding a floor in the Children's Department above the atrium, adding a floor in the Community Room to accommodate office space for Administration and Technical Services. The project also includes adding a mechanical room elevated at a higher level to lessen exposure (damage and financial) to future floods.  -- Kelly Foust
 


 Week of February 6, 2008

The Main Library closed due to Street Flooding. We received 2 inches of water in the garage, and we have taken on a bit of water in the basement. We are locating the Administration and Technical Services offices upstairs till we go into construction.


 Week of February 4, 2008

Future plans for the lower level include: a designated Volunteer space, a new Community Room and Book Cellar. Charles Construction is the project manager. Morrison Kattman Menze is the architect for the project.


 Week of December 3, 2007

The Main Library has reopened.  We are working with FEMA to mitigate the basement area and our Community Room.
 


 Week of November 5-9, 2007

The Children's and AV departments are being carpeted this week. The library has decided to combine these 2 desks into one and call it the "Information Desk". It will be located in front of the Southwest Window.
 


 Week of October 29-Nov.3., 2007

The staff finish painting the AV Offices and the Computer Lab.  A new floor is being put down in the lobby.

Many caring people have contacted us to offer donations of books. While we much appreciate any offers of assistance, the best way to help your library at this early stage of our rebuilding process is to donate funds.   We will gratefully accept donations to assist with recovery.  You may contribute to the Findlay-Hancock County Public Library Relief Fund at any Fifth Third Bank or send a check to: Fifth Third Bank, 337 South Main Street, Findlay, Ohio 45840.  The Findlay-Hancock County Public Library is funded through the Ohio Library Legislative Fund and does not receive funding via the United Way, the American Red Cross or any other local relief efforts. 


 


 Week of October 22-26, 2007

Children's Storytime is now being held at the Stately Raven Bookstore on Tuesdays and Thursdays at 10:30 a.m. This is open to Children of all ages.  1315 North Main Street, 419-427-2814

Volunteers help move all the Childrens Books and AV materials. New carpeting comes to these 2 departments on November 5th.

Library Book Truck Brigade makes an appearance at the Halloween Parade on October 23.
 


 Week of October 15-19, 2007

New phone system is installed and staff takes training on Voice Mail and the new features.

OPLIN calls the AT&T Engineers and they say we may have Internet service restored as early as mid-November.

Childrens and AV offices are painted a bright and cheery color.


 Week of October 7-13, 2007

New phone system arrives on Wednesday.

Tuesday October 9th: almost 200 patrons show up to check out books at the Arlington Branch Library. 

Library closed on Columbus Day, October 8th. The Book Drop at the Main Library is closed.


 Week of September 30-October 6, 2007

On October 2 Library Board contracts with Charles Construction to restore Lower Level and make improvements.

Inmates from the Hancock County Jail help with stripping old slate and landscaping.

Administration continues to prepare documentation for FEMA. 


 Week of September 23-29, 2007

Library begins to utilize volunteers from the community to help with Flood Recovery.


 Week of September 16-22, 2007

Re-assigned staff members help with clean up, shelve materials and landscaping.


 Week of September 9-15, 2007

Bookmobile and Arlington Branch re-open on September 10.


 Week of September 2-8, 2007

The Board of Trustee's held a public meeting at the Lodge at Riverbend Park on September 5th at 7:30 p.m. The meeting focused on Library Recovery efforts with a nice showing of concerned citizens, Hancock County Genealogy Society Members, retired staff members and Friends of the Library.

The first week of September Library Employees break up into teams and work quickly to establish services at Arlington Branch Library with a temporary Internet Cafe. The SEO Delivery Service is relocated to the Community Room at the Arlington Library, and the Bookmobile gets ready to open in locations around the county and in the library parking lot seven days a week.


 Week of August 26-September 1, 2007 

On August 30 two OPLIN engineers come to the Arlington Branch and re-route the internet so the Branch Library can reopen with internet running straight to Columbus on the T1 line.

The library employees man a booth at the Hancock County Fair August 29-September 3.

WebServer is relocated offsite and www.findlaylibrary.org reestablishes service on the WWW.

Main Library has been stripped of all contents in the lower level including drywall and ceiling tiles. Dehumidifiers are running in the upper level to control mold and save our 6 million dollars worth of library materials.


 Week of August 21, 2007 

As the flood receded, the library hired Tri-Weh, a recovery team out of Cincinnati to reclaim the Library.  Over a million gallons of water was pumped from the building in a 2 day period. All services were destroyed or damaged in the flood: furnace, electric, internet, phones, security, paging, fire alarm, sprinkler system etc. This also included the internet at our Arlington Branch, which comes directly through the Main Library in Findlay.

Early Tuesday Morning, on August 21, as much as 9 inches of rain fell over parts of Hancock County. To our East, parts of Wyandot County received 15 inches of rain in a few hours. The Blanchard River began to rise and flooding took place over much of the area.  Twelve library employees showed up for work, and spend most of the day bringing up essential materials from the Lower Level, which included the Clerk Treasurer's Office materials.  The rest of the employees were stuck in their homes with no way out. That evening the entire lower level went under water, and downtown Findlay experienced the worse flood in the city's history.

Monday, August 20 the library closed as usual at 8:30 p.m. A light rain was falling, with no indication of the incredible rainfall that was to happen just hours later.

Back


Summary,  Dick Taylor, Facilities Manager of the Findlay-Hancock County Public Library,  MAY 2008

 

Findlay Hancock Co. Public Library is located in Findlay, the Hancock Co. seat. Our area was originally part of the great black swamp, thus very flat, and drains slowly. Our building had a 15,000 sq ft furnished basement, an 11,000 sq ft underground parking garage, and a community room and lobby consisting of about 2000 sq ft at ground level. The collection and main operations are on our  25,000 sq ft upper level which lies about 5' above ground level.
 
On August 21st remnants of hurricane Erin passed over the Findlay area and stalled out, dumping almost 10" of rain through out the entire water shed of the  Blanchard river. The river runs thru the city of Findlay, and only several hundred feet from our building. Our flat topography results in a slow rise of river levels, our history of flood issues had educated us to know that this unusual amount of rain would cause massive flooding, so we closed the building the day after the storm and began moving important items upstairs. What we learned was that human nature had allowed us to "store" much more inventory in our available spaces than we had time and energy to move upstairs without a clear plan.
 
Only a small portion of the staff was able to make it to the building as roads began to close due to the rising water levels. We were able to move most of the electronics, files, books in storage, valuable supplies, and personal items up to the main floor. But without a solid flood evacuation plan, we were unable to save many supplies,  NO furnishings nor any of our mechanical & electrical systems. We received 90" of flood water in the basement, and several inches on the ground floor community room. Along with the muddy flood water, came sewage back up, a few small fish, and worst of all, our elevator control room was also located in the basement, and the hydraulic oil reservoir emptied 60 gallons of oil to the surface coating everything  with a slimy oily mud.
 
Our dollar loss for clean up, mitigation, inventory replacement, and reconstruction stands at over $2 million, but the untold loss of  community service is much harder to assess. We were "lucky" compared to many other county and city agencies, as our history of flooding pushed us to secure flood insurance after a more minor 1997 event. Our insurance paid for our entire cleanup and dry out, as well as a portion of our inventory replacement. And as a result of our proactive flood  response and insurance coverage, FEMA has come forward with a very responsible mitigation grant.
 
Our Main Library was closed to the public for over 12 weeks. During that time we extended hours at our one branch facility ( 10 miles south of Findlay ), and added stops and hours to our bookmobile service through out the city and county. We opened back up for major services on December 3, 2008, and began the slow process of  evaluating future needs and exposures. FEMA grant spending requires an effort to move affected services up and out of the reach of future flooding. We have  worked with an architect to add second floors in two areas, as well as constructing  a new elevated mechanical room on the outside of our building to accomplish this .
 
After a summer of construction, we will have all of our staff services and mechanical/electrical components up above  our 100yr flood level. We will also install a sanitary waste holding tank so that during future flood events we will be able to keep our restrooms open for staff and public use. Basement use in the future will be limited to public meeting rooms, staff  craft areas, our friends book sales area, and maintenance operations. We will require all inventory storage and furnishings to be wheel mounted,  and sized so that they fit into our elevator .
 

Back

 

© 2007-2008     Findlay-Hancock County Public Library